S. Laburnum Ave. Southbound Sidewalk

Project Status: Underway - Right of Way Acquisition

Estimated Cost: $3.0 Million
Start Date: 3rd Quarter, 2026
Estimated End Date: 2027

Magisterial District:   Varina  


Approximately 3,100-ft of new sidewalk along the western side of S. Laburnum Avenue from 600-ft south of Gay Avenue to Williamsburg Road. Project includes upgrades to existing transit bus stops within the project limits.  

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is underway. 
  • Utility relocation is not anticipated. 
  • Advertisement for construction is anticipated for 3rd Quarter, 2026. 
  • Construction is anticipated to commence in 3rd Quarter, 2026.