Staples Mill Road Sidewalk Phase 2

Project Status: Preliminary

Estimated Cost: TBD
Start Date: 2028
Estimated End Date: 2029

Magisterial District:   Brookland  


Project Description:

The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:

  • Continuous sidewalk along northbound Staples Mill Road from Meadow Pond Lane to existing sidewalk near the Britlyn North Subdivision.
  • Continuous sidewalk along northbound Staples Mill Road from Gracie Lane connecting to the existing sidewalk at the Latter-Day Saints Temple Property.

Estimated Schedule:

  • Design is anticipated to begin 3rd Quarter, 2026.
  • Right-of-way acquisition is anticipated to begin in 2028.
  • Utility relocation is anticipated to begin in 2028.
  • Advertisement for construction is anticipated for 2028.
  • Construction is anticipated to begin in 2028.