Three Chopt Road Sidewalk
This page content is archived for historical purposes.
Project Summary
- Project Status
- Completed
- Estimated Cost
- $1.2 million
- Start Date
- January 2023
- Estimated End Date
- June 2023
- Magisterial District
- Three Chopt Tuckahoe
Project Description
The County of Henrico will be constructing the following improvements:
- Sidewalk and curb ramp installation from Bexhill Road to Dinwiddie Avenue on both sides of Three Chopt Road.
- Pedestrian crosswalks with push button crossing signals at Camden Drive.
Estimated Schedule
- Design began March 2019.
- Right-of-way acquisition is complete.
- Utility relocation is complete.
- Advertisement for construction completed August 2022.
- Construction is anticipated to begin January 2023.
- Project completion is anticipated June 2023.
Three Chopt Road Sidewalk – Citizen Information Meeting Video
Progress to Date
- A citizen information meeting was held August 10, 2020 at the Ridge Elementary School bus loop.
- 100% plans final comments being addressed, bid documents and signatures in process.