Project Summary
- Project Status
- Completed
- Estimated Cost
- $250,000
- Start Date
- 3rd Quarter, 2024
- Estimated End Date
- 4th Quarter, 2024
- Magisterial District
- Brookland
Project Description
The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including:
- Add a crossing over Staples Mill Rd to Meadow Pond Lane to include ADA ramp(s).
- Add pedestrian signals and push-buttons.
Estimated Schedule: (Month Year)
- Design began in November 2022.
- Right-of-way acquisition is not anticipated.
- Utility relocation is not anticipated.
- Construction is 3rd quarter 2024