Multimodal Improvements on S. Laburnum Avenue over I-64​

Project Summary

Project Status
Underway - Design
Estimated Cost
$12.6 million
Start Date
2030
Estimated End Date
2032
Magisterial District
Fairfield   Varina

Project Description

The County of Henrico will be constructing improvements along S. Laburnum Avenue between Thornhurst Street and Gay Avenue. The following improvements will be constructed, including:  

  • ​​Sidewalk facilities, where currently not installed, on both sides of S. Laburnum Avenue north of the I-64 westbound off-ramp and on the west side of S. Laburnum Avenue south of the I-64 westbound off-ramp.  
  • ​Curb ramps, pedestrian crossing accommodations, proposed GRTC transit stop improvements, and intersection modifications​.  

Estimated Schedule

  • Design is underway.  
  • Right-of-way acquisition is anticipated to begin ​in 2028.​  
  • Utility relocation is anticipated to begin in 2029. ​  
  • Advertisement for construction is anticipated in 2029. ​  
  • Construction is anticipated to begin in 2030.​  

 