Multimodal Improvements on S. Laburnum Avenue over I-64
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $12.6 million
- Start Date
- 2030
- Estimated End Date
- 2032
Project Description
The County of Henrico will be constructing improvements along S. Laburnum Avenue between Thornhurst Street and Gay Avenue. The following improvements will be constructed, including:
- Sidewalk facilities, where currently not installed, on both sides of S. Laburnum Avenue north of the I-64 westbound off-ramp and on the west side of S. Laburnum Avenue south of the I-64 westbound off-ramp.
- Curb ramps, pedestrian crossing accommodations, proposed GRTC transit stop improvements, and intersection modifications.
Estimated Schedule
- Design is underway.
- Right-of-way acquisition is anticipated to begin in 2028.
- Utility relocation is anticipated to begin in 2029.
- Advertisement for construction is anticipated in 2029.
- Construction is anticipated to begin in 2030.
Amenities
Bus Stop
Pedestrian Signal
Sidewalk