Richmond-Henrico Turnpike Sidewalk
Project Status: Completed
Estimated Cost: $400,000 total
Start Date: September 2020
Estimated End Date: October 2020
Magisterial District: Fairfield
The County of Henrico will be constructing pedestrian access from Laburnum Avenue along the west side of Richmond-Henrico Turnpike and end at Pinalto Drive.
Estimated Schedule
- Design is complete
- Right-of-way acquisition is underway
- Utility relocation is complete
- Advertisement for Construction is complete
- Construction is anticipated to begin in September 2020
- Project completion is anticipated in October 2020