S. Laburnum/Route 5 Intersection Improvements
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $440,000
- Start Date
- 4th Quarter, 2026
- Estimated End Date
- 2027
- Magisterial District
- Varina
Project Description
Extension of an existing right turn lane on southbound S Laburnum Avenue at New Market Road (Route 5).
Estimated Schedule:
- Design is underway.
- Right-of-way acquisition is underway.
- Utility relocation is not anticipated.
- Advertisement for construction is not anticipated.
- Construction is anticipated to commence 4th Quarter, 2026.