S. Laburnum/Route 5 Intersection Improvements

Project Status: Underway - Design

Estimated Cost: $440,000
Start Date: 3rd Quarter, 2026
Estimated End Date: 2027

Magisterial District:   Varina  


Extension of an existing right turn lane on southbound S Laburnum Avenue at New Market Road (Route 5).

Estimated Schedule:

  • Design is underway.
  • Right-of-way acquisition is underway.
  • Utility relocation is not anticipated.
  • Advertisement for construction is anticipated for 3rd Quarter, 2026.
  • Construction is anticipated to commence 3rd Quarter, 2026.