Project Summary

Project Status
Completed
Estimated Cost
$137,773
Start Date
July 2023
Actual End Date
September 2023
Magisterial District
Brookland   Fairfield

Project Description

The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

 

  • Accommodations for pedestrians from Winfrey Road on the south side of Woodman Road to safely access the north side of Winfrey Road and/or the Fall Line Trail.    

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is anticipated to begin 06/2023.
  • Utility relocation is not anticipated. 
  • Advertisement for construction is not anticipated. 
  • Construction is anticipated to begin 09/2023.