Chamberlayne Farms Sanitary Sewer Project
This page content is archived for historical purposes.
Project Summary
- Project Status
- Completed
- Start Date
- December 2018
- Actual End Date
- July 2021
- Magisterial District
- Fairfield
Project Description
The Chamberlayne Farms/Chamberlayne Hills Sewer Project is to maintain the reliability of the sewer collection system by replacing or rehabilitating deteriorated sewer piping installed in the 1960’s.
Scope of Work:
- Rehabilitate approximately 6.6 miles of sewer piping
- Replace approximately 900 linear feet of sewer piping
- Replace/rehabilitate approximately 435 sanitary sewer service laterals
- Repave the area of the streets where “open cutting” is performed upon completion of the utility work.