County-Wide Pedestrian Intersection Accommodations
Project Summary
- Project Status
- Underway - Right of Way Acquisition
- Estimated Cost
- $1.7M
- Start Date
- 2027
- Estimated End Date
- 2027
- Magisterial District
- Brookland Fairfield Three Chopt Tuckahoe Varina
Project Description
The purpose of this project is to provide pedestrian crossing accommodations, including ADA ramps, crosswalks and pedestrian signals at the following four (4) intersections listed below:
- Gayton Road and Gaskins Road.
- Monument Avenue and Willow Lawn Drive.
- Old Nuckols Road/Wyndham Forest Drive and Nuckols Road.
- Quioccasin Road and Starling Drive.
Estimated Schedule
- Design is underway.
- Right-of-Way is underway.
- Utility relocation is not anticipated.
- Advertisement is anticipated to begin 2027.
- Construction is anticipated to begin 2027.