Gaylord Road Drainage Improvements
This page content is archived for historical purposes.
Project Summary
- Project Status
- Underway - Design
- Estimated Cost
- $900,000
- Start Date
- May 2025
- Estimated End Date
- Winter 2025/2026
- Magisterial District
- Three Chopt
Project Description
The County of Henrico will be addressing erosion and drainage issues within an existing ditch along the rear of the properties along Gaylord Road and Freestone Ave from Girard Ave to Parma Road.
Estimated Schedule:
- Design began in May 2024.
- Easement acquisition: Winter 2024/2025
- Advertisement for construction is anticipated to begin March 2025.
- Construction is anticipated to begin May 2025.
Progress to Date
- As of October/November, the project is in the Design & Plan Review Phase.
- A second Public Information Meeting is being held on 11/18/2024, at the Tuckahoe Middle School from 5:30 PM to 7:00 PM.
- See the following link to submit comments: Comment Form